Quote:
Originally Posted by M4 BAT
I called up BMW Canada, and they said my M4 order was accepted and production hasn't started yet! I am supposed to take delivery at the end of July. Is this wishful thinking?
How long does an M4 take to build from start to finish in production? 4 weeks?
Once the build is complete, how long does it take to get to the dealership in Canada? 2 weeks?
I'm guessing I won't get my car until sometime in August! This wait is killing me!!
|
I don't know exactly how long it took for mine but here is my time frame
Scheduled week 24 production. Confirmation received June 13 that my car was done and enroute to port.
According to the ocean carrier website (Wallenius) I checked on June 18 and it showed my car departed Bremerhaven on June 17. ETA Halifax June 30. I expect another 10-14 days to Calgary. I am guessing mid July delivery.
In total I would expect 5 weeks from start to delivery. Hope this helps.